PHirst Park Homes Pandi

As of June 15, 2021:

Phase 1 Land Development: 85%

  • No. of Housing Ongoing Construction: 336

Phase 2 Land Development: 80%

  • No. of Housing Ongoing Construction: 300
PHirst Park Homes Tanza

As of June 15, 2021:

Phase 1 Land Development: 100%

  • No. of Houses Constructed: 2014
  • No. of Housing Ongoing Construction: 25

Phase 2 Land Development: 90%

  • No. of Houses Constructed: 520
  • No. of Housing Ongoing Construction: 540

Clubhouse Construction: Completed

Amenity Nodes (PH1): Completed Outdoor Cinema

PHirst Park Homes San Pablo

As of June 15, 2021:

Phase 1 Land Development: 95%

  • No. of Houses Constructed: 90
  • No. of Housing Ongoing Construction: 404

Phase 2 Land Development: 75%

  • No. of Housing Ongoing Construction: 380
PHirst Park Homes Lipa

As of June 15, 2021:

Phase 1 Land Development: 95%

  • No. of Houses Constructed: 510
  • No. of Housing Ongoing Construction: 480

Phase 2 Land Development: 70%

  • No. of Housing Ongoing Construction: 280

Basketball Court Construction: 70%